A delay of two years and an additional cost of DKK 685 million.
SIGN UP FOR THE NEWSLETTER
The Italian contractor on the Storstrøm Bridge, SBJV, believes that the consequences of what they perceive as changed requirements for the bridge design, related to the risk of collisions or ship impacts, are a two-year delay and an additional cost ...
Contractor criticizes reinforcement of the Storstrøm Bridge
The contractor on the Storstrøm Bridge claims that modifications to the bridge design to prevent collisions cost them DKK 685 million and an extended construction period of two years