23948sdkhjf

Contractor criticizes reinforcement of the Storstrøm Bridge

The contractor on the Storstrøm Bridge claims that modifications to the bridge design to prevent collisions cost them DKK 685 million and an extended construction period of two years
A delay of two years and an additional cost of DKK 685 million. 

SIGN UP FOR THE NEWSLETTER


The Italian contractor on the Storstrøm Bridge, SBJV, believes that the consequences of what they perceive as changed requirements for the bridge design, related to the risk of collisions or ship impacts, are a two-year delay and an additional cost ...
Vil du have det hele med?
Prøv 30 dage for 0 kr.
Ingen binding eller kortoplysninger påkrævet.
Prøv nu
Køb et abonnement
Udforsk vores abonnementer, og vælg den løsning, der matcher dine behov.
Vælg dit abonnement
Job i fokus
Gå til joboversigten
Udvalgte artikler

Nyhedsbreve

Send til en kollega

0.109